A provisional sum is a monetary allowance included in a building contract for a particular work package whose final price is not yet established. In the JBCC context it relates to work supplied and installed by a subcontractor. It allows the tender to include a budget for the package while its detailed specification or procurement is finalised.
Why contractors include provisional sums
A design team may not have completed the mechanical services specification when the main building tender is issued. Instead of omitting the work entirely, the tender documents can include an allowance with a description of the intended scope. Tenderers can then consider the associated programme, coordination and attendance requirements.
How a provisional sum is adjusted
When the package is defined and procured, the contract administrator values the actual work under the agreed contract provisions. The original allowance is reconciled with the authorised value. Contractor profit, attendance and other charges must be treated according to the priced documents and contract, not assumed to be included or added automatically.
| Illustrative calculation, excluding VAT | Amount |
|---|---|
| Original contract sum | R1,000,000 |
| Included provisional sum | R60,000 |
| Authorised replacement package value | R75,000 |
| Net increase before other adjustments | R15,000 |
| Revised sum before other adjustments | R1,015,000 |
The example assumes no additional changes to separately priced attendance or profit. It illustrates the reconciliation method rather than a current subcontract price.
What to check before accepting a quote
- Identify the exact package covered and any exclusions.
- Ask what information is still outstanding and when the final price will be established.
- Confirm how subcontractors are selected and instructions authorised.
- Check the treatment of overheads, profit, attendance, VAT and programme effects.
- Ask whether the allowance is realistic for the required specification.
Provisional sum versus prime cost amount
A prime cost amount commonly relates to goods supplied to the site, with associated installation separately priced. A provisional sum in JBCC documents covers a subcontract work package. Informal residential quotations sometimes use these terms differently, so read the actual definition and adjustment clauses.
The ASAQS provisional sums guidance explains the JBCC approach. For a preliminary overall budget, use our house building cost calculator, then obtain detailed contract advice.
Frequently asked questions
Not necessarily. The agreed contract determines how the allowance is replaced or adjusted.
The reconciliation may reduce the contract sum, subject to the applicable valuation provisions and other adjustments.
Follow the contract’s authority and instruction procedures. An allowance alone does not authorise unrestricted expenditure.
Related construction questions
- What is a prime cost allowance?
- What is a construction contingency allowance?
- What is a bill of quantities?
Have More Construction Questions?
Explore our South African construction knowledge hub for practical answers about building materials, costs, regulations, construction methods and more.
Browse All Construction Questions