A bill of quantities (BOQ) is a structured document describing and measuring construction work so contractors can price it consistently. It usually lists work descriptions, units, quantities, rates and amounts. A quantity surveyor prepares it from drawings, specifications and applicable measurement rules. It supports tender comparison, cost control and contract administration.
What information does a BOQ contain?
A typical building BOQ separates work into trades such as earthworks, concrete, masonry, roofing, plumbing and finishes. Preliminaries address project-wide requirements such as establishment and management. Each measured item describes the work and its measurement unit, for example cubic metres of concrete, square metres of plaster or number of doors. The contractor inserts rates and calculates amounts.
Worked example of a small BOQ
| Illustrative item | Quantity | Rate | Amount |
|---|---|---|---|
| Concrete | 5 m³ | R2,000/m³ | R10,000 |
| Masonry | 40 m² | R450/m² | R18,000 |
| Plaster | 80 m² | R120/m² | R9,600 |
| Total | R37,600 |
These invented rates illustrate multiplication of quantity by rate, not current market prices. The example excludes other work, preliminaries and VAT. Actual item descriptions must define the required materials, workmanship and measurement basis.
How a BOQ helps compare contractors
When tenderers price the same measured document, the client can compare individual rates and identify unusually high or low items. The quantity surveyor can investigate omissions, qualifications and arithmetic errors before recommending a tender. A BOQ does not eliminate the need to read the drawings, specifications and contract conditions.
Are BOQ quantities fixed?
The contract determines whether quantities are subject to remeasurement or form part of a lump-sum arrangement. Changes in design, scope or measured work must be treated under the agreed valuation rules. A BOQ quantity is not automatically a supplier order quantity because cutting losses, packaging and procurement arrangements may differ from measurement rules.
For South African practice, consult the Association of South African Quantity Surveyors and its measurement resources. Use our concrete calculator and building materials cost calculator for preliminary quantities, not as replacements for a professionally prepared BOQ.
Frequently asked questions
No. A BOQ describes measured construction work and may include labour, materials, equipment and other pricing obligations. A material list focuses on procurement quantities.
A quantity surveyor commonly prepares it using coordinated design information and measurement rules.
Yes, where authorised changes or remeasurement apply under the contract. Maintain a clear record of adjustments.
Related construction questions
- What is a provisional sum in a building quote?
- Why do building quotes differ so much?
- How do you calculate material wastage?
Have More Construction Questions?
Explore our South African construction knowledge hub for practical answers about building materials, costs, regulations, construction methods and more.
Browse All Construction Questions