Estimating concrete quantities before ordering helps reduce shortages and material waste. A rectangular slab can be measured using its length, width and specified thickness.
Concrete volume formula
Volume (m³) = length (m) × width (m) × thickness (m). Convert millimetres to metres first: 150 mm equals 0.15 m. This is a calculation example, not a structural thickness recommendation.
Worked example
A 6 m by 4 m slab with a specified thickness of 150 mm requires 6 × 4 × 0.15 = 3.6 m³. An illustrative 5% allowance for placement losses and minor variations brings the estimate to 3.78 m³. Confirm the final order quantity and delivery increments with your supplier.
Account for changes in geometry
Thickened edges, beams and uneven subgrades can increase volume. Calculate additional sections separately without counting overlapping volumes twice. Divide irregular plans into measurable shapes.
Other materials
Reinforcement, laps, cover and spacing must follow the approved design. Formwork depends on exposed edges; ground-bearing slabs may require compacted fill and a moisture barrier. For site-mixed concrete, use approved mix proportions and yield rather than adding loose ingredient volumes directly.
Confirm dimensions, delivery access, placement and curing arrangements. Structural work must follow the engineer’s specification.
Read our concrete floor slab construction guide, browse material suppliers and find contractors.