Most building projects change in some way. A homeowner may select different finishes, an unexpected defect may be exposed or a designer may issue revised drawings. The problem is rarely the change itself: disputes arise when nobody agrees on the new price, completion date or exact scope.
A variation order is the written record of an authorised change. For the underlying definition, see what a construction variation order means.
1. Describe the change clearly
Record the location, affected drawing, material specification and work being added, removed or replaced. “Extra bathroom work” is not specific enough. Include quantities, quality requirements and relevant exclusions.
2. Identify who requested it
State whether the instruction came from the client, designer or another authorised representative. Check the contract for the required approval process. A verbal instruction may not meet the contract’s notice and authorisation rules.
3. Confirm the price adjustment
- Materials and labour.
- Equipment and subcontractors.
- Credits for omitted work.
- Waste removal and protection of completed areas.
- Applicable taxes and agreed overheads.
Compare the price against the original scope. The guides to estimates and quotations and bills of quantities help explain why missing items matter.
4. Record time impacts
Some changes delay following trades or require materials with longer lead times. Record any proposed extension and its reason. A variation does not automatically entitle a contractor to extra time; the contract and supporting evidence determine that.
5. Approve before starting
Use a numbered form with project details, scope, price, time impact, drawing references and signatures from authorised parties. Maintain a register showing pending, approved, rejected and completed changes. Provide the current instructions to everyone affected on site.
6. Reconcile at handover
Match approved changes to payment claims and the final account. Keep updated drawings and relevant warranties in the project records. Our contractor handover file guide explains common close-out documents.
Note: Structural, safety-related or approval-sensitive changes require appropriate professional review. This checklist is not legal advice and does not replace the building contract.