A prime cost allowance, often called a PC amount or PC sum, is a budgeted amount for goods or materials whose final selection or supply price is not yet established. In JBCC-based building contracts it concerns the delivered cost of goods obtained from a supplier as instructed by the principal agent. Installation and related contractor charges are normally addressed separately.
Where prime cost allowances are used
Common examples include sanitary fittings, taps, tiles and selected finishing products. A homeowner may know the required number of basins but may not have chosen the exact models before tender. The tender can include a supply allowance while the contractor prices the work required to install the fittings.
How a PC allowance affects the final price
Suppose a quote includes a hypothetical R12,000 allowance for delivered bathroom fittings, excluding VAT. The final authorised selection costs R16,500 on the same basis. The supply allowance increases by R4,500. If installation was separately priced at R5,000 and remains unchanged, the combined supply and installation amount moves from R17,000 to R21,500 before any other contract adjustments.
Do not assume that the difference is the entire final adjustment. The contract may prescribe how profit, handling, delivery, discounts or tax are calculated. If a new fitting requires different plumbing or additional supports, the installation scope may also need an authorised variation.
Prime cost versus provisional sum
| Allowance | Typical JBCC application |
|---|---|
| Prime cost amount | Delivered goods or materials |
| Provisional sum | Subcontract work including supply and installation |
| Contingency | Reserve for project uncertainty |
How to avoid unexpected finishing costs
Ask for a schedule of all PC amounts and the quantities they cover. Compare the allowances with actual supplier quotations for products of the intended quality. Check whether delivery to site, installation, consumables, storage and contractor charges are included elsewhere. Agree selections early enough to avoid delays and keep written records of approved changes.
For example, a tile allowance may cover the tiles but not adhesive, grout, trims or labour. Check the measured area and packaging allowance before selecting a product. A low PC amount can make an initial tender appear attractive while leaving a substantial cost increase later.
See the ASAQS prime cost amounts guidance for the JBCC definition and associated pricing considerations. Use our building materials cost calculator to compare hypothetical supply budgets.
Frequently asked questions
Under the usual JBCC approach it covers delivered goods, with installation separately priced. Check the actual contract.
Usually subject to approval and the contract’s adjustment procedure. Budget for the difference and any associated work.
Agree responsibility for delivery, defects, storage, installation and any contract credit before purchasing.
Related construction questions
- What is a provisional sum in a building quote?
- Why do building quotes differ so much?
- What is a construction variation order?
Have More Construction Questions?
Explore our South African construction knowledge hub for practical answers about building materials, costs, regulations, construction methods and more.
Browse All Construction Questions