An estimate is an indicative forecast of what construction work may cost, while a quotation offers a price for a stated scope on specified terms. An estimate is useful when design information is incomplete. A quotation normally provides a firmer basis for agreeing the work, but its legal effect and any permitted price changes depend on the actual terms and acceptance.
When should you request an estimate?
At the concept stage, a homeowner may know the approximate floor area and desired finishes but have no detailed drawings. An estimate helps assess affordability and compare design options. It should state the assumptions, scope, exclusions, date and level of uncertainty. As information improves, the quantity surveyor or contractor can refine the estimate. It is not a promise that the project can be completed for the stated amount.
What should a building quotation include?
A useful quotation identifies the contractor, client, project location, drawing revisions, work descriptions, price, applicable VAT, payment terms and validity period. It should explain exclusions, provisional sums, prime cost allowances and how changes will be valued. Ask whether the offer is a fixed price for defined work or subject to remeasurement, escalation or other adjustment provisions.
Worked example: estimate versus quotation
| Illustrative stage | Amount |
|---|---|
| Early estimate for a renovation | R250,000 |
| Detailed quotation after design | R285,000 |
| Authorised additional work | R15,000 |
| Revised contract amount | R300,000 |
All figures are hypothetical and assumed to use the same VAT basis. The detailed quotation exceeds the early estimate by R35,000 because the scope has been refined. The later R15,000 adjustment represents an authorised change, not an automatic entitlement to increase the price. The example assumes no other adjustments.
How to compare and accept quotations
Request written offers based on the same current drawings and specification. Check that the contractor has priced the intended quality and quantities. Compare the total payable amount, not just the headline price. Confirm the completion programme, payment milestones, defects responsibilities and the procedure for authorising additional work. Avoid accepting an offer until unresolved exclusions and allowances have been clarified.
For South African construction procurement and cost management, consult the Association of South African Quantity Surveyors and the Joint Building Contracts Committee for relevant contract documentation. Obtain professional advice where the agreement or price adjustment is disputed. Use our house building cost calculator to prepare an initial budget before obtaining detailed quotations.
Frequently asked questions
Not necessarily. Its effect depends on the wording, agreement and applicable law. Do not assume that calling a document an estimate settles every contractual question.
Yes. A quotation may specify a validity period. Confirm the price and terms if you accept after that period.
It may where the contract permits adjustments, authorised variations or other agreed changes. Ask for a documented explanation and check the contract before approving additional charges.
Related construction questions
- Why do building quotes differ so much?
- What is a construction variation order?
- What costs are often excluded from a house building quote?